Salt: Nedmag well TR-3 workover operation 2017

Salt producing well TR-3 workover operation Start execution: September 2017 End execution: October 2017 Result: Well back to salt production Depth (AH): Approx. 2000m>Depth (TVD): Approx. 1850m Project Summary Client: Nedmag Location: Veendam Wells: TR-3 Start Execution: September 2017 End Execution: October 2017 Target: Re-configure completion for future well production Result: Well back to salt […]

Read more

Salt: ESCO – Frisia well BAS-4 workover operation 2017

Salt producing well BAS-4 workover operation Start execution: October 2017 End execution: October 2017 Result: Well back to salt production Depth (AH): Approx. 2800mDepth (TVD): Approx. 2800m Project Summary Client: ESCO – Frisia Zout B.V. Location: Tzumarrum Wells: BAS-4 Start Execution: October 2017 End Execution: October 2017 Target: Re-configure completion for future well production Result: […]

Read more