Converting a dry hydrocarbon well into a geothermal well
Start execution: January 2011
End execution: July 2011
Result: Extended advisory (reports)
Depth (AH): 1980m
Project Summary
Client: | Brabantwater |
Location: | Nieuwendijk |
Wells: | NDK-01 |
Start: | January 2011 |
End: | July 2011 |
Target: | The conversion of a dry hydrocarbon well into a geothermal well |
Result: | Extended advisory (reports) |
Depths (AH): | Approx. 1980m |
Role of WEP: | Well Engineering Partners provided for this project the Planning, Well Design and Procurement services. WEP has all the knowledge about the NDK-01 well, since it was engineered and drilled under the supervision of WEP (in 2009 for NPN). |
Challenges: | n/a |