Geothermal: Green Well Westland Honselersdijk drilling a sidetrack

Geothermal well sidetrack HON-GT-01S2 Start execution: June 12th 2015 End execution: July 2nd 2015 Result: Successfully re-established well production Depth (AH): n/a Depth (TVD):n/a Project Summary Client:Green Well Westland Doublet:Honselersdijk Wells:HON-GT-01S2 (sidetrack) Start Execution:June 12th 2015 End Execution:July 2nd 2015 Target:Drill a sidetrack through the reservoir to re-establish well production Result:Successfully re-established well production Depths […]

Read more

Geothermal: Geothermie De Lier doublet delivery

Geothermal doublet LIR-GT-01 & LIR-GT-02 Start execution: May 20th 2014 End execution: August 2014 Result: Producing water with a temperature of 85 degrees Celsius Depth (AH): 2897m; 2880m Depth (TVD): approx. 2500m Project Summary Client:V.O.F. Geothermie De Lier (a cooperation of Harting Holland and A. de Bruijn en ZN. B.V.) Doublet:De Lier Wells:LIR-GT-01 & LIR-GT-02 […]

Read more

Geothermal: ECW Middenmeer two doublets delivery

Geothermal doublets MDM-GT-01 & MDM-GT-02; MDM-GT-03 & MDM-GT-04 Start execution: June 4th 2013 End execution: February 22nd 2014 Result: Two doublets drilled from same location. Both doublets are suitable for production and injection. Depth (AH): 2766m; 2589m; 2717m; 2652m Depth (TVD): All wells approx. 2400 m Project Summary Client:ECW Geoholding B.V. Doublet:Middenmeer Wells: MDM-GT-01 & […]

Read more

Geothermal: Floricultura Heemskerk doublet delivery

Geothermal doublet HEK‐GT‐01 & HEK‐GT‐02 Start execution: March 23rd 2013 End execution: January 2nd 2014 Result: Wells of 2600m TVD for heating 10 hectares of greenhouses Depth (AH): 3216m; 3200m Depth (TVD): Both approx. 2600m Project Summary Client:Ce-Ren Beheer / Floricultura Doublet:Heemskerk Wells:HEK‐GT‐01 & HEK‐GT‐02 Start Execution:March 23rd 2013 End Execution:January 2nd 2014 Target:Water flowrates […]

Read more

Geothermal: Koekoekspolder Ijsselmuiden restoring injectivity

Geothermal injector well KKP-GT-02 Start execution: January 2014 End execution:January 2014 Result: Injectivity is fully restored and the doublet is operational again. Depth (AH): n/a Depth (TVD):n/a Project Summary Client:Greenhouse Geopower Doublet:Koekoekspolder, Ijsselmuiden Wells:KKP-GT-02 Start Execution:January 2014 End Execution:January 2014 Target:Restoring the injectivity Result:Injectivity is fully restored and the doublet is operational again Depths (AH):n/a […]

Read more