Oil&Gas: Thru-Tubing Abandonment NAM Wells

Thru-Tubing Abandonment (TTA) Start Engineering: 2022 End execution:2025 Objective: P&A of multiple wells Client: Nederlandse Aardolie Maatschappij B.V. Location: Multiple Wells: Multiple Start Engineering: October 2022 End Execution: 2025 Objective: Thru-Tubing Abandonment (TTA), abandonment on a wire, of onshore NAM wells Role of WEP: Front End Design Well Engineering services, concept and detailed design Challenges: […]

Read more

CCS: TAQA (Porthos) – P18, Plug & Abandonment of multilateral well

Plug & Abandonment P18 Start Engineering: May 2021 End Execution: June 2022 Objective: Plug & Abandonment of multilateral well Depth (MD): 4000mDepth (TVD): 3500m Client: TAQA (Porthos) Location: Dutch sector North Sea Well: P18 Start Engineering: May 2021 End Execution: June 2022 Objective: Abandonment of multilateral well to make the reservoir suitable for CO2 injection […]

Read more

Oil&Gas: Abandonment well and drilling sidetrack in Middle East

Abandonment current well and Sidetrack drilling Start engineering:Q1 2020 (Expected) End date: Q2 2021 Objective: Collect data and bring well into production Depth (MD): 5000 mMD Depth (TVD): 4800 mTVD Project Summary Client:Operator in the Middle East Location:Middle East Wells:Existing well Start Engineering:Q1 2020 (Expected) End:Q2 2021 Project Objective:Collect data and bring well into production […]

Read more

Oil&Gas: Gasunie ZDW-A1A & – A1B Workover

Workover operations on ZDW-A1A & ZDW-A1B Start: 23 March 2020 End: 5 June 2020 Objective: Integration of cavern A1 into the existing underground gas storage Depth (AH): 1395m Depth (TVD): 1392m Project Summary Client:N.V. Nederlandse Gasunie (EnergyStock) Location:Zuidwending Wells:ZWD-A1A & ZWD-A1B Start operations:23 March 2020 End operations:5 June 2020 Objective:To integrate the cavern A1 into […]

Read more

Oil&Gas: Review well planning process

An independent review of a well planning process Execution date: March 2019 Target: Reviewing the well planning process Depth (AH):n/a Depth (TVD): n/a Project Summary Client:An energy company Loaction:Austria Wells:All wells in a new drilling campaign Target:Reviewing the well planning process Result:Recommendations were given to improve the well planning process and to reduce the drilling […]

Read more