Salt: Nedmag well TR-3 workover operation 2017

Salt producing well TR-3 workover operation Start execution: September 2017 End execution: October 2017 Result: Well back to salt production Depth (AH): Approx. 2000m>Depth (TVD): Approx. 1850m Project Summary Client: Nedmag Location: Veendam Wells: TR-3 Start Execution: September 2017 End Execution: October 2017 Target: Re-configure completion for future well production Result: Well back to salt […]

Read more

Salt: ESCO – Frisia well BAS-4 workover operation 2017

Salt producing well BAS-4 workover operation Start execution: October 2017 End execution: October 2017 Result: Well back to salt production Depth (AH): Approx. 2800mDepth (TVD): Approx. 2800m Project Summary Client: ESCO – Frisia Zout B.V. Location: Tzumarrum Wells: BAS-4 Start Execution: October 2017 End Execution: October 2017 Target: Re-configure completion for future well production Result: […]

Read more

Salt: Nedmag well TR-4 workover operation 2017

Brine producing well TR-4 Start execution: January 9th 2017 End execution: February 6th 2017 Result: The well back into production Depth (AH): 2066m Depth (TVD): 1932m Project Summary Client:Nedmag Doublet:Veendam Wells:TR-4 Start Execution:January 9th 2017 End Execution:February 6th 2017 Target:Fixing the completion string which was damaged in November 2017 Result:Bringing the well back into brine […]

Read more

Salt: Nedmag VE-4 Workover operation Phase I 2016

Magnesium brine producing well VE-4 workover operation Phase I Start execution: May 2016 End execution: July 2016 Result: Completion removed and measurements performed. Depth (Ah): 1745mDepth (TVD): 1635m Project Summary Client: Nedmag Location: Veendam Wells: VE-4 Start Execution: May 2016 End Execution: July 2016 Target: Removing the current completion from the well and performing measurements […]

Read more

Salt: ESCO – Frisia BAS-3O Workover operation 2016

Salt producing well BAS-3O workover operation Start execution: April 2016 End execution: April 2016 Result:Completed successfully a Hydraulic Workover Snubbing Operation. Depth (AH): 4632m Project Summary Client: Frisia Location: Harlingen Wells: BAS-3O Start Execution: April 2016 End Execution: April 2016 Target: The objective of the workover is to run the inner leaching string to new […]

Read more