Salt: ESCO – Frisia HWO

Salt producing well hydraulic workover operation Start execution: September 16th 2011 End execution: September 30th 2011 Result: Successfully completed the Hydraulic Workover Operation (HWO) Depth (AH): 2815m Project Summary Client: ESCO – Frisia Zout B.V. Location: Harlingen Wells: Salt producing well Start Execution: September 16th 2011 End Execution: September 30th 2011 Target: Repair a damaged […]

Read more

Salt: Akzo Nobel ISH-01 drilling

Salt exploration well ISH-01 drilling Start execution: December 2010 End execution: January 2011 Result: Successful drilling of exploration well ISH-01. Depth (AH): 971mDepth (TVD): 930m Project Summary Client: Akzo Nobel Location: Hengelo Wells: ISH-01 Start Execution: December 2010 End Execution: January 2011 Target: Drilling an exploration well for the development of a new cavern Result: […]

Read more

Salt: Arkema well PA31 sidetrack

Salt producing well PA31 sidetrack Start execution: April 24th 2010 End execution: May 25th 2010 Result: A 450m sidetrack to the existing salt producing well. Depth (AH): n/a Depth (TVD): n/a Project Summary Client: Arkema Location: Vauvert, France Wells: PA31 Start Execution: April 24th 2010 End Execution: May 25th 2010 Target: Drilling a sidetrack for […]

Read more

Salt: Nedmag Magenesium-brine wells workover

Several Magnesium-brine producing wells workover operations Start execution: May 13th 2008 End execution: June 17th 2008 Result: Successfull HWO operations on magnesium-brine producing wells. Depth (AH): n/aDepth (TVD): n/a Project Summary Client: Nedmag Location: Veendam Wells: Magnesium-brine producing wells Start Execution: May 13th 2008 End Execution: June 17th 2008 Target: Re-complete the wells with a […]

Read more

Salt: ESCO – Frisia well BAS-4 drilling

Drilling of vertical salt solution well BAS-4 Start execution: March 2nd 2004 End execution: April 16th 2004 Result: The delivery of the salt producing well BAS-4 Depth (AH): 2500m Depth (TVD): 2500m Project Summary Client: ESCO – Frisia Zout B.V. Location: Harlingen Wells: BAS-4 Start Execution: March 2nd 2004 End Execution: April 16th 2004 Target: […]

Read more