Salt: Nedmag TR-8 workover operation 2020

Salt well TR-8 workover (2020) Start Engineering: December 23rd, 2019 End execution: July 6th, 2020 Objective: Recomplete well with new dilution string Depth (MD): 1560mDepth (TVD): 1385m Project Summary Client: Nedmag Location: WHC-2 / Tripscompagnie Wells: TR-8 Start Engineering: December 23rd, 2019 End Execution: July 6th, 2020 Objective: Recomplete well with new dilution string Result: […]

Read more

Salt: Nedmag TR-5 workover

Salt well TR-5 workover Start Engineering: October 7th, 2019 End execution: June 26th, 2020 Objective: Remove the dual completion and perform a partial abandonment Depth (MD): 1642mDepth (TVD): 1590m Project Summary Client: Nedmag Location: WHC-2 / Tripscompagnie Wells: TR-5 Start Engineering: October 7th, 2019 End Execution: June 26th, 2020 Objective: Remove the dual completion from […]

Read more

Oil&Gas: Gasunie ZDW-A1A & – A1B Workover

Workover operations on ZDW-A1A & ZDW-A1B Start: 23 March 2020 End: 5 June 2020 Objective: Integration of cavern A1 into the existing underground gas storage Depth (AH): 1395m Depth (TVD): 1392m Project Summary Client:N.V. Nederlandse Gasunie (EnergyStock) Location:Zuidwending Wells:ZWD-A1A & ZWD-A1B Start operations:23 March 2020 End operations:5 June 2020 Objective:To integrate the cavern A1 into […]

Read more

Salt: ESCO – Frisia BAS-3O Workover 2019

Salt producing well BAS-3O workover Start Engineering: December 4th, 2018 End execution: Septembre 30th, 2019 Result: The cavern was plugged, in preparation for full abandonment the well Depth (MD): 4444mDepth (TVD): 2558m Project Summary Client: ESCO – Frisia Zout B.V. Location: Pietersbierum, BAS-123 Wells: BAS-3O Start Engineering: December 4th, 2018 End Execution: September 30th, 2019 […]

Read more

Geothermal: CLG well intervention

Geothermal well CAL-GT-04 intervention Start engineering: March 12th, 2018 Expected end execution: June 1st, 2018 Target: Succesfully well intervention Depth (AH):ESP installation @ 472m, Inhibitorline @ 2740m Project Summary Client:Californie, Liepzig, Gielen (CLG) Geothermie Doublet:Californie Wells:CAL-GT-04 Start Engineering:March 12th, 2018 End Execution:June 1st, 2018 Target:Pulling the ESP on 7” production tubing, replacing / modifying the […]