Salt: Frisia BAS-3O Plug & Abandonment 2021

Plug & Abandonment Start Engineering: November 2021 End execution: January 2022 Objective: Permanently plug & abandon high deviation solution salt well Depth (MD): 4733mDepth (TVD): 2847m Client: Frisia Zout B.V. Location: BAS-123 / Pietersbierum Wells: BAS-3O Start Engineering: November 2021 End Execution: January 2022 Objective: Permanently plug & abandon high deviation solution salt well Depths […]

Read more

Salt: Nedmag TR-9 workover 2021

Salt well TR-9 workover Start Engineering: October 2021 End execution: December 2021 Objective: Re-complete well Depth (MD): 2451m Depth (TVD): 1812m Client: Nedmag BV Location: WHC-2 / Tripscompagnie Wells: TR-9 Start Engineering: October 2021 End Execution: December 2021 Objective: Re-complete well Depths (MD): 2451m Depths (TVD): 1812m Role of WEP: WEP provided project planning, tendering […]

Read more

Oil&Gas: Abandonment well and drilling sidetrack in Middle East

Abandonment current well and Sidetrack drilling Start engineering:Q1 2020 (Expected) End date: Q2 2021 Objective: Collect data and bring well into production Depth (MD): 5000 mMD Depth (TVD): 4800 mTVD Project Summary Client:Operator in the Middle East Location:Middle East Wells:Existing well Start Engineering:Q1 2020 (Expected) End:Q2 2021 Project Objective:Collect data and bring well into production […]

Read more

Salt: Nedmag TR-7 workover 2020

Salt well TR-7 workover Start Engineering: November 2018 End execution: November 2020 Objective: Re-complete well Depth (MD): 1726mDepth (TVD): 1480m Project Summary Client: Nedmag BV Location: WHC-2 / Tripscompagnie Wells: TR-7 Start Engineering: November 2018 End Execution: November 2020 Objective: Re-complete well Depths (MD): 1726m Depths (TVD): 1480m Role of WEP: Engineering and planning support […]

Read more

Salt: Nedmag TR-8 workover operation 2020

Salt well TR-8 workover (2020) Start Engineering: December 23rd, 2019 End execution: July 6th, 2020 Objective: Recomplete well with new dilution string Depth (MD): 1560mDepth (TVD): 1385m Project Summary Client: Nedmag Location: WHC-2 / Tripscompagnie Wells: TR-8 Start Engineering: December 23rd, 2019 End Execution: July 6th, 2020 Objective: Recomplete well with new dilution string Result: […]

Read more