Salt: Nedmag TR-5 Partial abandonment
Project Description
The objective of this operation was to remove a blockage in the bottom of the production tubing of Nedmag’s VE-5 salt well.
The first phase of the operations was carried out in February 2024 using a combined wireline and mini coil unit. Using a jetting tool run on mini coil a salt blockage was jetted away and afterwards the bottom part of the production tubing was cut in order to ensure full cavern access.
Later on, salt blockages re-appeared but after several clean out runs the well was brought back into production.
Role of WEP
Delivery of the concept design and detailed design document, Drilling program. Assisting in the procurement process, preparing HSSE documents, providing operational support in the field and from the office.
Overview
Client
Nedmag BVLocation
WHC-2 / TripscompangnieWell
TR-5Date
Start drilling: 15 June 2023
End execution: 15 May 2024Objective
Partial abandonment of a salt wellDepth
Depth (MD): 1642m
Depth (TVD): 1590m