Salt: Nedmag TR-5 Partial abandonment

Project Description

The objective of this operation was to remove a blockage in the bottom of the production tubing of Nedmag’s VE-5 salt well.

The first phase of the operations was carried out in February 2024 using a combined wireline and mini coil unit. Using a jetting tool run on mini coil a salt blockage was jetted away and afterwards the bottom part of the production tubing was cut in order to ensure full cavern access.

Later on, salt blockages re-appeared but after several clean out runs the well was brought back into production.

Role of WEP

Delivery of the concept design and detailed design document, Drilling program. Assisting in the procurement process, preparing HSSE documents, providing operational support in the field and from the office.

Overview

  • Client
    Nedmag BV
  • Location
    WHC-2 / Tripscompangnie
  • Well
    TR-5
  • Date
    Start drilling: 15 June 2023
    End execution: 15 May 2024
  • Objective
    Partial abandonment of a salt well
  • Depth
    Depth (MD): 1642m
    Depth (TVD): 1590m

View project on the map

Name
Salt well TR-5
Description
Remove a blockage in the bottom of the production tubing of Nedmag’s VE-5 salt well
Start Execution
June 15th, 2023
End Execution
May 15th, 2024
The objective of this operation was to remove a blockage in the bottom of the production tubing of Nedmag’s VE-5 salt well