Salt ESCO – Frisia well BAS-4 workover operation 2017
Project Description
During production, the lower section of the well completion became damaged. Although the damage was not directly influencing the well production it restricted full-bore access to the cavern for logging operations and was considered to potentially lead to further issues in the future if not remediated.
In preparation for the workover with Hydraulic workover unit (HWU) the lower, damaged, section of the completion was cut and dropped in the cavern. After this logging was performed to assess the well condition.
With the HWU new sections were added to the inner completion string, after which the well was successfully brought back into production.
For this project, Well Engineering Partners provided project planning, tendering engineering, coordination, management, and supervision for the project while other companies provided materials and services.
Challenges
High pressure salt production well.
Role of WEP
Well Engineering Partners provided project planning, tendering engineering, coordination, management and supervision for the project while other companies provided materials and services.
Overview
Client
ESCO - Frisia Zout B.V.Location
TzumarrumWell
BAS-4Date
Start drilling: 01 October 2017
End execution: 31 October 2017Objective
Re-configure completion for future well production.Depth
Depth (MD): Approx. 2800m
Depth (TVD): Approx. 2800m