Salt: Dow K08 Workover

Salt well K08

Start Engineering: 2024
End execution:June 2024

Objective: Workover POOH inner string and investigate outer leaching string

Depth (MD): 1340m
Depth (TVD): 1340m

Client: Dow Deutschland Anlagengesellschaft mbH
Location: Ohrensen
Wells: K08
Start Engineering: 2024
End Execution: June 2024
Objective: Workover POOH inner string and investigate outer leaching string
Depths (MD): 1340m
Depths (TVD): 1340m
Role of WEP: Project management, well engineering, procurement support, planning, work program and HSE documents. Supervision onsite and workover management/engineering from the office.

Project Description

The objective of this project was to POOH the inner leaching string and investigate the outer leaching string of Dow’s cavern well K08.

The inner string was completely pulled out of hole with a hydraulic workover unit (HWU). After the HWU operation the outer leaching string was investigated with wireline.

The operation was quickly lined up. After the request to line up the HWU operation and start operations was 2 weeks.

All objectives were met.


Rig complete