Salt: ESCO – Frisia well BAS-4 workover operation 2017

Salt producing well BAS-4 workover operation

Start execution: October 2017
End execution: October 2017

Result: Well back to salt production

Depth (AH): Approx. 2800m
Depth (TVD): Approx. 2800m

Project Summary

Client: ESCO - Frisia Zout B.V.
Location: Tzumarrum
Wells: BAS-4
Start Execution: October 2017
End Execution: October 2017
Target: Re-configure completion for future well production
Result: Well back to salt production
Depths (AH): Approx. 2800m
Depths (TVD): Approx. 2800m
Role of WEP: Well Engineering Partners provided project planning, tendering engineering, coordination, management and supervision for the project while other companies provided materials and services.
Challenges: High pressure salt production well

Project Description

During production, the lower section of the well completion became damaged. Although the damage was not directly influencing the well production it restricted full-bore access to the cavern for logging operations and was considered to potentially lead to further issues in the future if not remediated.

In preparation for the workover with Hydraulic workover unit (HWU) the lower, damaged, section of the completion was cut and dropped in the cavern. After this logging was performed to assess the well condition.

With the HWU new sections were added to the inner completion string, after which the well was successfully brought back into production.

For this project, Well Engineering Partners provided project planning, tendering engineering, coordination, management, and supervision for the project while other companies provided materials and services.