Salt: Nedmag VE-5 Well cleanout operations

Project Description

The objective of this operation was to remove a blockage in the bottom of the production tubing of Nedmag’s VE-5 salt well.

The first phase of the operations was carried out in February 2024 using a combined wireline and mini coil unit. Using a jetting tool run on mini coil a salt blockage was jetted away and afterwards the bottom part of the production tubing was cut in order to ensure full cavern access.

Later on, salt blockages re-appeared but after several clean out runs the well was brought back into production.

Role of WEP

Well engineering, planning,  writing programs and HSE documents. During operations, SSV and WSE onsite and office support.

Overview

  • Client
    Nedmag BV
  • Location
    WHC-1/Borgercompagnie
  • Well
    VE-5
  • Date
    Start drilling: 08 January 2024
    End execution: 30 April 2024
  • Objective
    Well cleanout opeations
  • Depth
    Depth (MD): 2636m
    Depth (TVD): 1738m

View project on the map

Name
Salt well VE-5
Description
Well cleanout operations
Start Execution
January 8th, 2024
End Execution
April 30th, 2024
The objective of this operation was to remove a blockage in the bottom of the production tubing of Nedmag’s VE-5 salt well