Salt: Nedmag well TR-4 workover operation 2017

Project Description

The brine producing well TR-4 was one of the best producers for Nedmag with high magnesium concentration, but the completion string was damaged in November 2016.

The objective of this workover was to bring the well back into production. This was accomplished by retrieving the current completion strings, running and drilling-in a new 7” x 5” completion and installing a new 4 ½” dilution string.

For this project, Well Engineering Partners provided project planning, tendering engineering, coordination, management, and supervision for the project while other companies provided materials and services.

In order to re-complete the well, BPC’s Space Saver II HWU was used. Operations on the well started on January the 9th and was successfully finished on February 6th.

Challenges

n/a

Role of WEP

WEP provided for this project the Workover programs, Material & Service procurement, Contracting support, Workover operations management, Workover operations supervision and Detailed design.

Overview

  • Client
    Nedmag
  • Location
    Veendam
  • Well
    TR-4
  • Date
    Start drilling: 09 January 2017
    End execution: 06 February 2017
  • Objective
    Fixing the completion string which was damaged in November 2016.
  • Depth
    Depth (MD): 2066m
    Depth (TVD): 1932m

View project on the map

Name
Brine producing well TR-4
Description
Fixing the completion string which was damaged in November 2016.
Start Execution
January 9th, 2017
End Execution
February 6th, 2017
Fixing the completion string which was damaged in November 2016.