Oil&Gas: Abandonment well and drilling sidetrack in Middle East
Project Description
- Current well:
- Remove upper completion
- Spot cement abandonment plugs
- Sidetrack 1:
- Drill 8 ½” section
- Install and cement 7” liner
- Drill 6” section
- Perform wireline logs
- Abandonment of leg
- Sidetrack 2:
- Drill 6” section
- Perform wireline logs
- Install lower and upper completion
Challenges
General: Logistics of remote location and impact Covid-19. Operations: Losses during the drilling.
Role of WEP
Design the abandonment of the current well, Sidetrack-1 drilling and abandonment program and ST2 drilling program and completion. As well to plan and supervise all field operations. Also support is being provided for the procurement of services and materials and HSE documentation.
Overview
Client
Operator in the Middle EastLocation
Well
Existing wellDate
Start drilling: 01 January 2021
End execution: 30 June 2020Objective
Collect data and bring well into production.Depth
Depth (MD): 5000m
Depth (TVD): 4800m