Oil&Gas: Abandonment well and drilling sidetrack in Middle East

Project Description

  • Current well:
    • Remove upper completion
    • Spot cement abandonment plugs
  • Sidetrack 1:
    • Drill 8 ½” section
    • Install and cement 7” liner
    • Drill 6” section
    • Perform wireline logs
    • Abandonment of leg
  • Sidetrack 2:
    • Drill 6” section
    • Perform wireline logs
    • Install lower and upper completion

Challenges

General: Logistics of remote location and impact Covid-19. Operations: Losses during the drilling.

Role of WEP

Design the abandonment of the current well, Sidetrack-1 drilling and abandonment program and ST2 drilling program and completion. As well to plan and supervise all field operations. Also support is being provided for the procurement of services and materials and HSE documentation.

Overview

  • Client
    Operator in the Middle East
  • Location
  • Well
    Existing well
  • Date
    Start drilling: 01 January 2021
    End execution: 30 June 2020
  • Objective
    Collect data and bring well into production.
  • Depth
    Depth (MD): 5000m
    Depth (TVD): 4800m

View project on the map

Name
Abandonment current well and Sidetrack drilling
Description
Collect data and bring well into production.
Start Execution
January 1st, 2021
End Execution
June 30th, 2020
General: Logistics of remote location and impact Covid-19. Operations: Losses during the drilling.