Other: Kanton Basel Landschaft MMA-1 / MSC-1 Evalutation Well Integrity
Project Description
For the canton of Basel-Landschaft, WEP assessed the integrity of two monitoring wells near Basel, Switzerland.
The work began with a review of the well data following construction and concluded with wireline logging on both wells. The resulting data was processed, analyzed, and visualized to develop casing profiles, after which a final report was prepared. Both were completed safely and without incident.
Role of WEP
WEP’s scope included well engineering, planning, reporting, and development of the wireline program. During the operational phase, WEP delivered onsite SSV and office support.
Overview
Client
Kanton Basel LandschaftLocation
Basel, SwitzerlandWell
MMA-1 / MSC-1Date
Start: 08 August 2025
End: 21 May 2026Objective
Evaluate the well integrity of two monitoring wells by performing wireline logs.Depth
Depth (MD): 142 / 143 m (vertical)
Depth (TVD): N/A