Salt

Salt: Nedmag TR-6 workover 2022

Project Description

The objective of the workover was to remove the existing 3½” dilution string and 5” production string from the well, perform wireline investigations on the 10¾” casing and recomplete with a new 5” x 4½” drill-in completion and a new 2⅞” dilution string.

The lower section of the old completion, was damaged, restricting efficient production from the well.

The inner completion string was retrieved with a hydraulic workover unit. A floating mud cap was required to control the well, so the dilution and production string could be safely pulled out of the hole, then new drill-in 5” x 4 ½” completion was RIH.

The drill-in completion was equipped with a sacrificial BHA; including a mud motor (PDM) and a directional MWD. The drilling took longer than expected due to difficulties with the MWD. Eventually the new production string was drilled near vertical to TD and the dilution string was successfully run in the hole.

The project was finished with zero HSE related non-conformities.

Challenges

Challenges to cut the old completion string due to deformations and slow progress on drilling operations by run the new completion with controlled parameters to guarantee the verticality of the trajectory.

Role of WEP

Engineering and planning support on program and HSE documents. Operational support onsite and back-office.

Overview

  • Client
    Nedmag BV
  • Location
    WHC-2 / Tripscompagnie
  • Well
    TR-6
  • Date
    Start drilling: 03 January 2022
    End execution: 25 February 2022
  • Objective
    Re-complete well.
  • Depth
    Depth (MD): 1863m
    Depth (TVD): 1798m

View project on the map

Name
Salt well TR-6 workover
Description
Engineering and planning support on program and HSE documents. Operational support onsite and back-office.
Start Execution
January 3rd, 2022
End Execution
February 25th, 2022
The objective of the workover was to remove the existing 3½” dilution string and 5” production string from the well, perform wireline investigations on the 10¾” casing and recomplete with a new 5” x 4½” drill-in completion and a new 2⅞” dilution string.