Geothermal: Aardwarmtecluster I KKP B.V. Production Well Delivery

Project Description

Aardwarmtecluster I KKP B.V. exploits a doublet for exactly one decade. So far since the start, roughly 48 million cubic metres of commercial gas have been replaced by geothermal heat.

Adding an extra production well to the existing doublet is what this project is all about. Well design/engineering phase started in 2019. The permit/license project took over two years. In 2021 the procurement started. Milestone of spudding the well was achieved in late May 2022

Keywords: WBM only, Rotary + PDM, open hole stimulation, internally coated production string, triplet.

Challenges

Simultaneous operations (since exploitation and drilling on the same site).

New Technology:
Research project: HIPE, open hole / aquifer stimulation, radial jet drilling, internally coated production string.

Role of WEP

Engineering, Procurement, Drilling Supervision, HSE and subsequent support (on-site and office based) during the well delivery phase.

Overview

  • Client
    Aardwarmtecluster I KKP B.V.
  • Location
    Koekoekspolder
  • Well
    KKP-GT-03
  • Date
    Start drilling: 01 February 2019
    End execution: 15 July 2022
  • Objective
    Well delivery of additional production well to existing doublet.
  • Depth
    Depth (MD): 2000m
    Depth (TVD): 2000m

View project on the map

Name
KKP-GT-03
Description
Well delivery, additional production well to existing doublet.
Start Execution
February 1st, 2019
End Execution
July 15th, 2022
Well delivery, additional production well to existing doublet.