Geothermal: Aardwarmtecluster I KKP B.V. Production Well Delivery
Project Description
Aardwarmtecluster I KKP B.V. exploits a doublet for exactly one decade. So far since the start, roughly 48 million cubic metres of commercial gas have been replaced by geothermal heat.
Adding an extra production well to the existing doublet is what this project is all about. Well design/engineering phase started in 2019. The permit/license project took over two years. In 2021 the procurement started. Milestone of spudding the well was achieved in late May 2022
Keywords: WBM only, Rotary + PDM, open hole stimulation, internally coated production string, triplet.
Challenges
Simultaneous operations (since exploitation and drilling on the same site).
New Technology:
Research project: HIPE, open hole / aquifer stimulation, radial jet drilling, internally coated production string.
Role of WEP
Engineering, Procurement, Drilling Supervision, HSE and subsequent support (on-site and office based) during the well delivery phase.
Overview
Client
Aardwarmtecluster I KKP B.V.Location
KoekoekspolderWell
KKP-GT-03Date
Start drilling: 01 February 2019
End execution: 15 July 2022Objective
Well delivery of additional production well to existing doublet.Depth
Depth (MD): 2000m
Depth (TVD): 2000m