Geothermal

Geothermal: Hoogweg Aardwarmte Luttelgeest triplet delivery

Project Description

In May ‘18 the 3rd well was successfully drilled and completed. On May 22nd the VarioRig VDD370.2 was fully demobilized. The last phase of the wells delivery phase commenced on June 4th ’18. Whereas the first well was tested with the VarioRig VDD370.2 placed over the well, wells LTG-GT-02 & 03 will be tested without the rig in place. Upon completion of the well tests the three wells will be logged (baseline integrity survey). Next phase is to hook up the wells to the surface facilities to start producing geothermal energy/heat.

Challenges

Small tolerances (hole sizes vs. steel sizes), due to maximized casing sizes to anticipate on high flow rates expectations

Role of WEP

For this project, Well Engineering Partners is responsible for the well designs, project planning, tendering and coordination of the contracting of the materials and services suppliers. During the execution phase WEP provides the coordination, management and supervision for the project while other companies will provide materials and services.

Overview

  • Client
    Hoogweg Aardwarmte
  • Location
    Luttelgeest
  • Well
    LTG-GT-01 & LTG-GT-02 & LTG-GT-03
  • Date
    Start drilling: 01 June 2017
    End execution: 04 June 2018
  • Objective
    Completion of well delivery; well test (rigless) to determine potential triplet.
  • Depth
    Depth (MD): 1951m; 2317m; 2264m
    Depth (TVD): 1863m; 1806m; 1820m

View project on the map

Name
Geothermal triplet LTG-GT-01 & LTG-GT-02 & LTG-GT-03
Description
Completion of well delivery; well test (rigless) to determine potential triplet
Start Execution
June 1st, 2017
End Execution
June 4th, 2018
Completion of well delivery; well test (rigless) to determine potential triplet.