Geothermal Hoogweg Aardwarmte Luttelgeest triplet preperations
Project Description
Preparations for this project started mid ‘17 with the concept and detailed design of the triplet wells phase, followed by the process of securing the permits and materials and services required to deliver the wells. In January ’18 three conductor pipes have been successfully installed. In February Drilltec’s VarioRig VDD370.2 will be rigged up to commence with drilling the first of three wells. Each well is planned to be delivered within 30 days, including well test.
For this project, Well Engineering Partners is responsible for the well designs, project planning, tendering and coordination of the contracting of the materials and services suppliers. During the execution phase WEP provides the coordination, management and supervision for the project while other companies will provide materials and services.
Challenges
n/a
Role of WEP
Well Engineering Partners is responsible for the well designs, project planning, tendering and coordination of the contracting of the materials and services suppliers. During the execution phase WEP provides the coordination, management and supervision for the project while other companies will provide materials and services.
Overview
Client
Hoogweg AardwarmteLocation
LuttelgeestWell
LTG-GT-01 & LTG-GT-02 & LTG-GT-03Date
Start drilling: 01 June 2017
End execution: 31 December 2017Objective
Heated water for greenhousesDepth
Depth (MD): LTG-GT-01: 1935m; LTG-GT-02: 2139m; LTG-GT-03: 2289m
Depth (TVD): LTG-GT-01: 1845m; LTG-GT-02: 1779m; LTG-GT-03: 1794m