Trias Westland Delivery of Doublet NLW-GT-01 & NLW-GT-02
Project Description
The delivery of the geothermal doublet for Trias Westland.
Challenges
Drilling to the Trias (over 4000m depth).
Role of WEP
The following services are delivered by WEP:
- Check on Detailed Well Design
- Tendering and coordination of the contracting of the materials (incl. drilling rig) and services suppliers
- Drilling Program
- HSE Documents
- Drilling Management
- Drilling Supervision (NDSV)
- Cost Control
- End of Well Report
- Well Testing (together with VeeGEO)
Overview
Client
Trias Westland B.V.Location
Naaldwijk, The NetherlandsWell
NLW-GT-01 & NLW-GT-02Date
Start drilling: 02 October 2017
End execution: 29 June 2018Objective
The target is the Trias. Delivery of a geothermal doubletDepth
Depth (MD): 4560m; 2680m
Depth (TVD): 4063m; 2525m