Geothermal doublet PLD-GT-01 & PLD-GT-02
Start execution: August 18th 2016
End execution: November 6th 2016
Result: Warm water for heating of greenhouses
Depth (AH): 2799m; 2712m
Depth (TVD): 2460m; 2435m
Project Summary
Client: | Aardwarmte Vogelaer |
Doublet: | Poeldijk |
Wells: | PLD-GT-01 & PLD-GT-02 |
Start Execution: | August 18th 2016 |
End Execution: | November 6th 2016 |
Target: | Warm water for heating of greenhouses |
Result: | Drilled and tested doublet |
Power (thermal): | 15 MWTh |
Depths (AH): | PLD-GT-01: 2799m; PLD-GT-02: 2712m |
Depths (TVD): | PLD-GT-01: 2460m; PLD-GT-02: 2435m |
Role of WEP: | WEP was responsible for the well design and supervision during the execution of the project. |
Challenges: | n/a |
Project Description
After a period of intensive (engineering) preparations, drilling for geothermal heat has started in August 2016 in Poeldijk, the Netherlands. The DrillTec VDD370.2 VarioRig spudded the first well on August 18th, 2016. Two wells were planned to be drilled forming a geothermal doublet for heating several greenhouses in the Poeldijk area.
Drilling and testing operations were finished for Aardwarmte VogelaerĀ on November 6th, 2016. Wells PLD-GT-01 and PLD-GT-02 were drilled and tested successfully using the DrillTec Vario rig.
Well Engineering Partners provides engineering during the preparations and drilling management during the execution on behalf of Aardwarmte Vogelaer.