Geothermal: Feasibility design geothermal project

Engineering support in the feasibility stage Start engineering: November 2020 End engineering: November 2020 Objective:Drafting a feasibility design for a geothermal project Depth (TVD): 2000 m – 3500m Project Summary Client:Municipality (in the Netherlands) Start Engineering:November 2020 End Engineering:November 2020 Project Objective:Drafting a feasibility design for a geothermal project in the Netherlands. Result:Complete feasibility design […]

Read more

Salt: Frisia HVM-02 drilling

Salt well HVM-02 drilling Start Engineering: January 2018 End execution: November 2020 Objective: Design and drill an ERD salt well, from the FRISIA Havenmond location to the Havenmond concession. Depth (MD): 4950mDepth (TVD): 3021m Project Summary Client: FRISIA Location: Havenmond Wells: HVM-02 Start Engineering: January 2018 End Execution: November 2020 Objective: Design and drill a […]

Read more

Salt: Nedmag TR-7 workover 2020

Salt well TR-7 workover Start Engineering: November 2018 End execution: November 2020 Objective: Re-complete well Depth (MD): 1726mDepth (TVD): 1480m Project Summary Client: Nedmag BV Location: WHC-2 / Tripscompagnie Wells: TR-7 Start Engineering: November 2018 End Execution: November 2020 Objective: Re-complete well Depths (MD): 1726m Depths (TVD): 1480m Role of WEP: Engineering and planning support […]

Read more