Nedmag VE-5 Well cleanout operations
Project Description
The objective of this operation was to remove a blockage in the bottom of the production tubing of Nedmag’s VE-5 salt well.
The first phase of the operations was carried out in February 2024 using a combined wireline and mini coil unit. Using a jetting tool run on mini coil a salt blockage was jetted away and afterwards the bottom part of the production tubing was cut in order to ensure full cavern access.
Later on, salt blockages re-appeared but after several clean out runs the well was brought back into production.
Challenges
This well follows an existing well design however the inclination of this well with a maximum 53 degree will be challenging to drill. Additionally, this well will be drilled from an existing location which results in challenges during rigup and will require coordination of concurrent operations.
Role of WEP
Delivery of the concept design and detailed design document, Drilling program. Assisting in the procurement process, preparing HSSE documents, providing operational support in the field and from the office.
Overview
Client
Nedmag BVLocation
MiddenmeerWell
VE-5Date
Start drilling: 15 June 2017
End execution: 17 July 2024Objective
Well cleanout opeationsDepth
Depth (MD): 2251m
Depth (TVD): 3251m