Salt

Salt: Nedmag three well interventions

Project Description

Well Engineering Partners completed successfully three Hydraulic Workover Snubbing Operations (HWO). In the 7 weeks, 2 wells were brought back into production and in the third well, the completion was retrieved as deep as possible. All was done under approximately 120 bar high wellhead pressure. All workover operations were carried out with a Hydraulic Workover Unit (HWU) of Balance Point Control.

Each well had a different scope:

1) Well 1: the injection point was raised above the production point in order to regain production.

2) Well 2: the 7” x 5” production string was retrieved and wireline measurements were performed.

3) Well 3: the damaged 5” x 4 ½” was retrieved and recompleted with a drillable 5” x 4 ½” completion.

In the first well the 3 ½” tubing string was pulled out of the hole. Then the 5” x 4 ½” tubing was lifted up 20m. Perforating guns were run through the lifted tubing string and the 7 5/8” casing was perforated between. After perforations, the 5” x 4 ½” tubing was landed back to its original depth and the 3 ½” tubing string was run back into the hole. After the 3 ½” was successfully hung off, the unit was moved to the 2nd well.

At the 2nd well the 4 ½” dilution string was pulled out of the hole. Then the 7” part of the casing string was plugged and pulled out of the hole. With a fishing job with a mechanical cutter, the remaining 5” fish was cut as deep as possible and retrieved to surface. After the well was cleared a detailed wireline survey (cement, caliper, etc.) was carried out. The well was suspended by a 7” suspension string.

The HWU moved to the 3rd well. Initially, the 3 ½” dilution string was pulled out of the hole. Then the well was killed with floating mud cap and kill mud. After this, the 5” x 4 ½” completion was retrieved. Wireline investigations confirmed good well integrity. A 5” x 4 ½” completion with drill-in BHA was run in hole and drilled from 1700 m to 1900m. A wireline memory tool was used for directional measurements during drilling. At TD, the BHA was severed with a wireline severing tool.

Challenges

n/a

Role of WEP

Well Engineering Partners provided project planning, tendering engineering, coordination, management and supervision for the project while other companies provided materials and services.

Overview

  • Client
    Nedmag
  • Location
    Veendam
  • Well
    Three salt producing wells
  • Date
    Start drilling: 01 December 2013
    End execution: 28 February 2014
  • Objective
    Execution of Hydraulic Workover Snubbing Operations (HWO) on three different wells.
  • Depth
    Depth (MD): n/a
    Depth (TVD): n/a

View project on the map

Name
Three salt producing well interventions
Description
Successful completion of three Hydraulic Workover Snubbing Operations (HWO).
Start Execution
December 1st, 2013
End Execution
February 28th, 2014
Execution of Hydraulic Workover Snubbing Operations (HWO) on three different wells.

Other recent projects