Salt

Salt: Dow K08 Workover

Project Description

The objective of this project was to POOH the inner leaching string and investigate the outer leaching string of Dow’s cavern well K08.

The inner string was completely pulled out of hole with a hydraulic workover unit (HWU). After the HWU operation the outer leaching string was investigated with wireline.

The operation was quickly lined up. After the request to line up the HWU operation and start operations was 2 weeks.

All objectives were met.

Role of WEP

Project management, well engineering, procurement support, planning, work program and HSE documents. Supervision onsite and workover management/engineering from the office.

Overview

  • Client
    Dow Deutschland Anlagengesellschaft mbH
  • Location
    Ohrensen
  • Well
    K08
  • Date
    Start drilling: 01 June 2024
    End execution: 28 June 2024
  • Objective
    Workover POOH inner string and investigate outer leaching string
  • Depth
    Depth (MD): 1340m
    Depth (TVD): 1340m

View project on the map

Name
Salt well K08
Description
Workover POOH inner string and investigate outer leaching string
Start Execution
June 1st, 2024
End Execution
June 28th, 2024
Workover POOH inner string and investigate outer leaching string