Salt: Dow K08 Workover
Project Description
The objective of this project was to POOH the inner leaching string and investigate the outer leaching string of Dow’s cavern well K08.
The inner string was completely pulled out of hole with a hydraulic workover unit (HWU). After the HWU operation the outer leaching string was investigated with wireline.
The operation was quickly lined up. After the request to line up the HWU operation and start operations was 2 weeks.
All objectives were met.
Role of WEP
Project management, well engineering, procurement support, planning, work program and HSE documents. Supervision onsite and workover management/engineering from the office.
Overview
Client
Dow Deutschland Anlagengesellschaft mbHLocation
OhrensenWell
K08Date
Start drilling: 01 June 2024
End execution: 28 June 2024Objective
Workover POOH inner string and investigate outer leaching stringDepth
Depth (MD): 1340m
Depth (TVD): 1340m