Salt: ESCO – Frisia BAS-3O sidetrack 2014

Project Description

After the successful permanent abandonment of the old BAS-3 cavern operations were continued to clean out the upper section of the well. Thereafter a sidetrack with 450m outstep was drilled to create a new production cavern in the salt formation.

In order to be able to sidetrack at sufficient depth further attempts were made to retrieve the 11-3/4” casing to the minimum required sidetracking depth. Casing retrieval was done by cutting & pulling in sections. When this was unsuccessful even for short casing sections (30m) it was decided to mill ahead. After milling through a stuck section three 100m sections were successfully cut & pulled, after which the whipstock was placed and window milled.

Drilling the 12-1/4” section with a rotary steerable (RSS) assembly was successful, after which the hole was enlarged to 14” with an underreamer. Drilling operations were performed with OBM in the hole to prevent locally highly reactive clay from swelling. Throughout the drilling operations, hole cleaning was actively monitored at surface by cutting returns and pressure monitoring.

When running the flush 11-3/4” casing it was expected to reach a point of no return at ca. 2/3 of the total depth (4300m), where the PUW of the casing would exceed the rig load limit. Therefore casing weights were actively monitored throughout the casing trip. Even though the total open hole time exceeded 14 days the casing was landed at the pre-planned depth.

An 8-1/2” section was drilled through the salt & underreamed to 15”, after which the production casing and injection tubing were installed. Circulation tests were performed with good results.

Challenges

Achieving sidetrack point, heavy 11-3/4” casing string, small casing-casing clearances, directional profile, hole cleaning.

Role of WEP

Well Engineering Partners provided project planning, tendering engineering, coordination, management and supervision for the project while other companies provided materials and services.

Overview

  • Client
    ESCO - Frisia Zout B.V.
  • Location
    Pietersbierum
  • Well
    BAS-3O (sidetrack)
  • Date
    Start drilling: 07 September 2014
    End execution: 21 January 2015
  • Objective
    Drilling & completing a side-track to establish a new salt production cavern.
  • Depth
    Depth (MD): 4742m
    Depth (TVD): 2855m

View project on the map

Name
Salt producing well BAS-3O sidetrack
Description
Drilling & completing a side-track to establish a new salt production cavern
Start Execution
September 7th, 2014
End Execution
January 21st, 2015
Drilling & completing a side-track to establish a new salt production cavern.