Salt Nedmag well TR-3 workover operation 2017

Project Description

The lower section of the well completion, became damaged, restricting efficient production from the well.

With the Hydraulic workover unit (HWU) the inner completion string was retrieved. The production string was cut above the damaged section and the upper section of the outer completion retrieved. To re-establish entrance to the cavern system, milling operations were performed. To assess the downhole situation at the Hold-up-depth (HUD) real-time wireline camera runs were performed both prior to the milling operations and after. Once an exit was confirmed the drill-in completion was run in hole.

The drill-in completion was equipped with a sacrificial BHA; including a mud motor (PDM) and a directional MWD. The sacrificial MWD was included to drill a vertical hole through the cavern section, for improved stability and prevent damage to the tubing. On previous similar operations, directional control was performed with multiple single-shot wireline surveys every stand drilled. Due to the inclusion of the MWD the multiple wireline runs could be eliminated, which proved a benefit both to operational time and to HSE. In addition, the continuous directional control allowed for an overall higher ROP due to a faster feedback on BHA directional behavior.

For this project, Well Engineering Partners provided project planning, tendering engineering, coordination, management, and supervision for the project while other companies provided materials and services.

Challenges

High pressure salt production well.

Role of WEP

Well Engineering Partners provided project planning, tendering engineering, coordination, management and supervision for the project while other companies provided materials and services.

Overview

  • Client
    Nedmag
  • Location
    Veendam
  • Well
    TR-3
  • Date
    Start drilling: 01 September 2017
    End execution: 31 October 2017
  • Objective
    Re-configure completion for future well production
  • Depth
    Depth (MD): Approx. 2000m
    Depth (TVD): Approx. 1850m

View project on the map

Name
Salt producing well TR-3 workover operation
Description
Re-configure completion for future well production.
Start Execution
September 1st, 2017
End Execution
October 31st, 2017
Re-configure completion for future well production