Salt: Nedmag VE2 Partial abandonment

Project Description

The objective of this project was to place two plugs as part of the abandonment of Nedmag’s VE-2 salt well. VE-2 was drilled in 1982, and a first plug was placed in 1998.

The operations were executed using BPC’s pipe puller. First, a cement wiper plug which had been there since 1998 was drilled out. A cement plug was placed at the depth of the Vlieland Clay. The 10 ¾” casing was cut and the top 268 m were pulled out of hole, a cement plug was placed to seal off the Chalk.

All operations were completed without incidents or accidents. Currently the well is being monitored, in 2024 the environmental plug will be placed, finalizing the abandonment.

Role of WEP

Well engineering, planning, execution, writing designs, programs and HSE documents. During operations, SSV and WSE onsite and office support.

Overview

  • Client
    Nedmag B.V.
  • Location
    WHC-1/Borgercompagnie
  • Well
    VE-2
  • Date
    Start drilling: 01 March 2022
    End execution: 30 September 2022
  • Objective
    The objective of this project was to place two plugs as part of the abandonment of Nedmag’s VE-2 salt well.
  • Depth
    Depth (MD): 1543m
    Depth (TVD): 1402m

View project on the map

Name
Salt well VE-2 Partial abandonment
Description
The objective of this project was to place two plugs as part of the abandonment of Nedmag’s VE-2 salt well.
Start Execution
March 1st, 2022
End Execution
September 30th, 2022
The objective of this project was to place two plugs as part of the abandonment of Nedmag’s VE-2 salt well. VE-2 was drilled in 1982, and a first plug was placed in 1998.