Salt: Nedmag TR-8 workover operation 2020
Project Description
After the pre-engineering phase, the first step was to clean the inside of the 2 7/8” dilution tubing. Inside was cleaned with BH coil, operations were between 6 May and 9 May.
On 20 May the BPC snubbing unit was mobilized and subsequently rigged up. The 2 7/8” dilution string was snubbed out of hole, the 5” production string and the wellhead were inspected and the new 2 7/8” was snubbed in hole. On 31 May the unit was demobilized.
Challenges
No major challenges.
Role of WEP
Engineering and planning support on program and HSE documents. Operational support onsite and back-office.
Overview
Client
NedmagLocation
WHC-2 / TripscompagnieWell
TR-8Date
Start drilling: 23 December 2019
End execution: 06 July 2020Objective
Recomplete well with new dilution string.Depth
Depth (MD): 1560m
Depth (TVD): 1385m