Salt

Salt: Nedmag TR-8 workover operation 2020

Project Description

After the pre-engineering phase, the first step was to clean the inside of the 2 7/8” dilution tubing. Inside was cleaned with BH coil, operations were between 6 May and 9 May.

On 20 May the BPC snubbing unit was mobilized and subsequently rigged up. The 2 7/8” dilution string was snubbed out of hole, the 5” production string and the wellhead were inspected and the new 2 7/8” was snubbed in hole. On 31 May the unit was demobilized.

Challenges

No major challenges.

Role of WEP

Engineering and planning support on program and HSE documents. Operational support onsite and back-office.

Overview

  • Client
    Nedmag
  • Location
    WHC-2 / Tripscompagnie
  • Well
    TR-8
  • Date
    Start drilling: 23 December 2019
    End execution: 06 July 2020
  • Objective
    Recomplete well with new dilution string.
  • Depth
    Depth (MD): 1560m
    Depth (TVD): 1385m

View project on the map

Name
Salt well TR-8 workover (2020)
Description
Recomplete well with new dilution string.
Start Execution
December 23rd, 2019
End Execution
July 6th, 2020
Recomplete well with new dilution string.