LTG-GT-07, 08, 09, 10 & 11
Start Engineering: March 2021
End Execution: May 2022
Objective: Well delivery
Depth (MD): 2400m
Depth (TVD): 1900m
Client: | Hoogweg Aardwarmte B.V. |
Location: | Luttelgeest |
Wells: | LTG-GT-07, 08, 09, 10 & 11 |
Start Engineering: | March 2021 |
End Execution: | May 2022 |
Objective: | Well delivery |
Depths (MD): | 2400m |
Depths (TVD): | 1900m |
Role of WEP: | Engineering, Procurement, Drilling Supervision, HSE and subsequent support (on-site and office based) during the well delivery phase. |
Challenges: | Execution during COVID-19, simultaneous operations (exploitation and drilling on the same site). |
Project Description
WEP worked together with DrillTec, Enconsol, INCO drilling, Akros, Rollman, GeoService, NOV, Odfjell Well Services, Fangmann, Deep Drill, Iteco, HP Well Screen and Titan to successfully deliver five new wells to Hoogweg Aardwarmte B.V.
In just over five months, five wells have been delivered with the VarioRig. Three smaller-sized injection wells, and two larger-sized production wells. All wells were delivered in three sections (excluding stovepipe/conductor)
What remains is to test the wells as well as to install some of the final completion hardware. This is planned to be executed “lean” (meaning without a drilling rig) upcoming summer. The objective for Hoogweg is to have the new wells ready to be exploited before the start of autumn.
Key words: WBM only, PDM only, under reaming, XLOT, multi-skidding operations, extended flowline