Salt well TR-8 workover (2020)
Start Engineering: December 23rd, 2019
End execution: July 6th, 2020
Objective: Recomplete well with new dilution string
Depth (MD): 1560m
Depth (TVD): 1385m
Project Summary
Client: | Nedmag |
Location: | WHC-2 / Tripscompagnie |
Wells: | TR-8 |
Start Engineering: | December 23rd, 2019 |
End Execution: | July 6th, 2020 |
Objective: | Recomplete well with new dilution string |
Result: | The workover oepration was successful. |
Depths (MD): | 1560m |
Depths (TVD): | 1385m |
Role of WEP: | Engineering and planning support on program and HSE documents. Operational support onsite and back-office |
Challenges: | No major challenges. |
New technology: | n/a |
Project Description
After the pre-engineering phase, the first step was to clean the inside of the 2 7/8” dilution tubing. Inside was cleaned with BH coil, operations were between 6 May and 9 May.
On 20 May the BPC snubbing unit was mobilized and subsequently rigged up. The 2 7/8” dilution string was snubbed out of hole, the 5” production string and the wellhead were inspected and the new 2 7/8” was snubbed in hole. On 31 May the unit was demobilized