Geothermal doublet PNA‐GT‐01 & PNA‐GT‐02
Start execution: March 9th 2010
End execution: July 9th 2010
Result: Geothermal capacity for 42,500 sqm of greenhouses
Depth (AH): 2869m; 2860m
Depth (TVD): Both approx. 2500m
Project Summary
Client: | Ammerlaan B.V. |
Doublet: | Pijnacker |
Wells: | PNA‐GT‐01 & PNA‐GT‐02 |
Start Execution: | March 9th 2010 |
End Execution: | July 9st 2010 |
Target: | Deviated wells with 2500m TVD |
Result: | Geothermal capacity for 42,500 sqm of greenhouses |
Power (thermal): | 7 MWTh |
Depths (AH): | PNA‐GT‐01: 2869m; PNA‐GT‐02: 2860m |
Depths (TVD): | PNA‐GT‐01: Approx. 2500m; PNA‐GT‐02: Approx. 2500m |
Role of WEP: | WEP/PGMi was responsible for the geology report, material&service procurement, detailed design, drilling programs, contracting support and drilling management&supervision |
Challenges: | n/a |
Project Description
In Pijnacker, the Netherlands, several agricultural companies signed a collaboration for the development of geothermal energy. WEP/PGMi was responsible for the realization of a geothermal doublet for Ammerlaan Land & hydroponics BV. This company situated in Pijnacker has 42,500 square meters in which plants from 50cm to 4 meters in different types and sizes are beeing produced. WEP/PGMi was responsible for the geological aspects, well design and drilling supervision for this geothermal doublet with deviated wells to a vertical depth of 2500 meters and with a space between injection and production well at deepest point of 1400 meters.